M42 Junction 5 (Solihull)
The northbound entry slip road of the M42 at junction 5 will be closed overnight from 10.00pm to 5.00am from Monday 13 October 2008 to Tuesday 14 October 2008 (1 night) for repairs to the overhead signals for Midlands TechMAC. A diversion route will be clearly signposted.
M6 Junction 8 (Ray Hall)
The link road from the M5 northbound carriageway to the M6 northbound carriageway at M6 junction 8 will be closed overnight from 9.00pm to 5.00am from Monday 13 October 2008 to Wednesday 15 October 2008 (2 nights) for carriageway resurfacing and road marking. A diversion route will be clearly signposted.
M6 Junction 8 (Ray Hall)
The link road from the M5 northbound carriageway to the M6 northbound carriageway at M6 junction 8 will be closed overnight from 9.00pm to 5.00am from Friday 17 October 2008 to Saturday 18 October 2008 (1 nights) for carriageway resurfacing and road marking. A diversion route will be clearly signposted.
Issued on behalf of the Highways Agency by COI News & PR West Midlands
Enquiries to Filippa St Aubin d’Ancey / Annie Harris on 0121 352 5516 / 5518
Road
Location
Start Date
End Date
Works Description
Traffic Management Type
A38
M5 Junction 4 Island
16-Oct-08
17-Oct-08
Inner lane closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC
Lane Closure
A40
Various locations
16-Sep-08
31-Oct-08
Lane 1 closure with switching in operation 0800 - 1630 hrs and 2000 - 0530 hrs for retensioning work
Lane Closure with Switching
A40
Wilton Roundabout, Wilton, Herefordshire
29-Sep-08
21-Nov-08
Various lane closures in operation 0930 - 1530 hrs for carriageway reconstruction
Lane Closure
A40
Near Pencraig
6-Oct-08
14-Nov-08
40mph speed limit with verge works in operation 0930 - 1530 hrs to remove loose rocks and vegetation clearance
Speed Restriction
A4123
975 Wolverhampton Road, Oldbury (opposite Asda)
6-Jun-08
17-Oct-08
Various lane closures 0930 - 1530 hrs for new access and traffic signal improvement work for new development
Lane Closure
A4123
Coseley to Warley Woods, both directions
8-Oct-08
18-Oct-08
Nightly lane 1 or 2 closures as required 2100 - 0500 hrs for renewal of road markings at various locations
Lane Closure
A4123
Birmingham New Road junction with Sedgley Road
9-Oct-08
15-Oct-08
Lane 1 closure 24hrs for emergency repair to gas leak
Lane Closure
A4123
Opposite Junction of Woocroft Avenue, Tipton, northbound
13-Oct-08
13-Oct-08
Lane 1 closure from 0930 - 1530 hrs for street lighting works
Lane Closure
A4123
A4123 Southbound. From Birchley Island to Clent Road.
13-Oct-08
20-Oct-08
Nightly lane 1 running with convoy working from 1800 - 0600 for resurfacing
Convoy Working
A446
Stonebridge Island to M6 junction 4, both directions
13-Oct-08
15-Oct-08
Daily lane 1 or 2 closures as required from 0930 - 1530 hrs for grass cutting, sweeping, cleansing and gully emptying at various locations
Lane Closure
A45
M42 junction 6 to Stonebridge Island, both directions
16-Oct-08
17-Oct-08
Daily lane 1 or 2 closures as required from 0930 - 1530 hrs for grass cutting, sweeping, cleansing and gully emptying at various locations
Lane Closure
A458
Wollaston, Halfway House
13-Oct-08
13-Oct-08
Traffic signals in operation 0930 - 1530 hrs for pole erection
Traffic Signals
A46
Marraway Island to Longbridge Island, both directions
9-Jun-08
16-Jul-10
Provisional nightly lane 1 closures from 2000 - 0600 hrs for Major Works For M40 Junction 15 Longbridge Bypass Works
Lane Closure
A46
B4463 Junction, Sherbourne
9-Jun-08
16-Jul-10
Verge works for Major Works For M40 Junction 15 Longbridge Bypass Works
Lane Closure
A46
A3400 to A439 northbound
21-Sep-08
12-Jan-09
24hour lane 1 closure for geotechnical works including a 40mph speed limit through the works
Lane Closure
A46
Trelleborg site, Ashchurch Industrial Estate
13-Oct-08
28-Nov-08
Traffic signals or Stop/Go in operation 0930 - 1530 hrs for works to access points and improvements to pedestrian crossing point
Traffic Signals
A46
Bishopton to Marraway
13-Oct-08
18-Oct-08
Traffic Signals in operation 1900 - 0530 hrs for renewing of cats eyes
Traffic Signals
A46
Evesham bypass, between Broadway island and Twyford island
15-Oct-08
16-Oct-08
Narrow lane in operation 1000 - 1500 hrs for sign erection
Width Restriction
A465
Belmont to Llangue
9-Oct-08
17-Oct-08
Stop & Go in operation from 0930-1530 for Gully Emptying
Stop/Go Boards
A49
A4103 Roundabout, Holmer, Hereford
1-Sep-08
17-Nov-08
Partial lane closures in place 0930 - 1530 hrs for construction of pedestrian refuges and alterations to existing refuge. Construction of a new footway/cycleway in verge
Width Restriction
A49
Bayston Hill - Salway Arms
13-Oct-08
17-Oct-08
Stop & go boards in operation daily from 0930 - 1530 hrs for gully repairs at various locations
Lane Closure
A49
Bayston Hill
14-Oct-08
14-Oct-08
Stop & go boards in operation fro 0930 - 1530 hrs for sign replacement
Stop/Go Boards
A49
By the Yew Tree Public House, Peterstow
15-Oct-08
15-Oct-08
Traffic signals in operation 0930 - 1530 hrs to restore BT service
Traffic Signals
A49
Onibury level crossing
16-Oct-08
16-Oct-08
Stop and Go in operation 0930 - 1530 hrs to recover BT cables
Stop/Go Boards
A5
M6 Junction 12 to Gailey, westbound
13-Oct-08
17-Oct-08
Traffic signals in operation daily from 0930 - 1530 hrs for drainage works
Traffic Signals
A5
Churncote to Gledrid
13-Oct-08
17-Oct-08
Stop & go boards in operation daily from 0930 - 1530 hrs for gully emptying at various locations
Stop/Go Boards
A5
Emstrey Island
13-Oct-08
19-Dec-08
Various nightly lane and total closure (dates TBC) from 2000 - 0600 hrs for traffic signalisation works
Lane Closure
M40
Junction 16 to M42 junction 3a, both directions
26-Aug-08
28-Feb-09
Various daily & nightly 24 hour closures for ATM works
Lane Closure
M40
Junction 16 to Junction 14, both directions
25-Sep-08
30-Sep-09
24hour narrow lanes in operation with 50mph speed limit. Contraflow in operation 24 hours with 50mph speed limit from January 2009. This will include narrow lanes on J15 slip roads
Lane Closure
M40
Junction 15 to M42 junction 3a, both directions
13-Oct-08
17-Oct-08
Daily mobile closures from 0930 - 1530 hrs for grass cutting and litter picking at various locations
Mobile Lane Closure
M40
Junction 16 southbound exit slip road
13-Oct-08
14-Oct-08
Lane 2 closure from 2100 - 0500 hrs for sign replacement works
Lane Closure
M42
Junction 3a to junction 7, both directions
21-Jul-08
15-Nov-08
Various nightly lane closures from 2100 - 0500 hrs for footpath construction to Emergency Refuge Bays (No Bank Holiday working)
Lane Closure
M42
Junction 3a to junction 7, both directions
28-Jul-08
13-Dec-08
Various nightly lane closures from 2100 - 0500 hrs for road marking and road stud renewal (No Bank Holiday Working)
Lane Closure
M42
Junction 7 to junction 9, both directions
26-Aug-08
28-Aug-09
Various daily & nightly 24 hour closures for ATM works to include narrow lanes, hard shoulder running and 50mph speed limit
Lane Closure
M42
Junction 1 to junction 2, both directions
13-Oct-08
14-Oct-08
Northbound hard shoulder and southbound lane 3 closures from 2100 - 0500 hrs for survey works
Lane Closure
M42
Junction 7 to junction 5, southbound
13-Oct-08
14-Oct-08
Lanes 2 & 3 closed followed by lane 1 as required from 2100 - 0500 hrs for structural inspections. To include lane 2 on J6 entry slip road
Lane Closure with Switching
M42
Junction 4 slip roads
13-Oct-08
16-Oct-08
Nightly lane 1 closure followed by lane 2 closure as required from 2100 - 0500 hrs for the installation of diversion route signage
Lane Closure
M42
Junction 5 northbound entry slip road
13-Oct-08
14-Oct-08
Full overnight closure from 2200 - 0500 hrs for repairs to overhead signals. To include lane 3 running on main carriageway
Carriageway Closure
M42
Junction 1 to junction 2, both directions
14-Oct-08
15-Oct-08
Southbound hard shoulder and northbound lane 3 closures from 2100 - 0500 hrs for survey works
Lane Closure
M42
Junction 5 to junction 6, northbound
14-Oct-08
15-Oct-08
Lanes 2 & 3 closed followed by lane 1 as required from 2100 - 0500 hrs for structural inspections. To include lane 1 on J6 entry slip road
Lane Closure with Switching
M42
Junction 5 to junction 4, southbound
15-Oct-08
16-Oct-08
Lanes 2 & 3 closed from 2100 - 0500 hrs for repairs to overhead cameras
Lane Closure with Switching
M42
Junction 7 to junction 6, southbound
15-Oct-08
16-Oct-08
Lanes 2 & 3 closed followed by lane 1 as required from 2100 - 0500 hrs for structural inspections. To include lane 1 on J7 entry slip road
Lane Closure with Switching
M42
Junction 3a, M42 east to M42 north link road
16-Oct-08
17-Oct-08
Hard shoulder closure from 2100 - 0500 hrs for the installation of diversion route signage
Lane Closure
M42
Junction 2 eastbound exit slip road
16-Oct-08
17-Oct-08
Lane 1 followed by lane 2 closure as required from 2100 - 0500 hrs for the installation of diversion route signage
Lane Closure
M42
Junction 3 eastbound exit slip road
16-Oct-08
17-Oct-08
Lane 1 followed by lane 2 closure as required from 2100 - 0500 hrs for the installation of diversion route signage
Lane Closure
M42
Junction 5 to junction 4, southbound
16-Oct-08
17-Oct-08
Single lane running from 2130 - 0600 hrs for repairs to overhead signals, to include lane closure on J5 entry slip road
Lane Closure with Switching
M42
Junction 6 to junction 7, northbound
16-Oct-08
17-Oct-08
Lanes 2 & 3 closed from 2130 - 0530 hrs for presetting of narrow lanes for ATM works
Lane Closure
M42
Junction 3 slip roads
17-Oct-08
18-Oct-08
Lane 1 followed by lane 2 closure as required from 2100 - 0500 hrs for the installation of diversion route signage
Lane Closure
M5
Strensham services southbound entry slip
21-Dec-07
30-Jun-09
Hard shoulder closure 24 hrs for prevention of illegal parking
Lane Closure
M5
Various locations between junction 9 and 5
1-Sep-08
19-Dec-08
Lane 3 closure with switching in operation 2000 - 0600 hrs for Retensioning
Lane Closure with Switching
M5
Various locations between junction 9 and 5
22-Sep-08
20-Nov-08
Mobile closure in operation 0930 - 1530 hrs for gully emptying
Mobile Lane Closure
M5
M6 junction 8 to M5 junction 9, both directions
30-Sep-08
13-Dec-08
Daily hard shoulder closures from 0930 - 1530 hrs for installation of driver location signs at various locations
Lane Closure
M5
M5 Junction 4a, M42 south to M5 north link road
30-Sep-08
31-Oct-08
Full overnight closure (30/9/08) from 2100 - 0500 hrs for the installation of concrete safety barriers following earlier RTC. There will then be a 24hour lane H/S closure
Lane Closure
M5
Junction 4a, both directions
6-Oct-08
17-Oct-08
Daily hard shoulder closures from 0800 - 1700 hrs for construction / installation of new communications cabinet site
Lane Closure
M5
Junction 5 to junction 9, both directions
13-Oct-08
16-Oct-08
Mobile lane 3 closure 1900 - 0530 hrs for street lighting work
Mobile Lane Closure
M5
Junction 1 northbound entry slip road
14-Oct-08
15-Oct-08
Lane 2 closure from 2100 - 0500 hrs for routine maintenance works
Lane Closure
M5
Junction 9 to junction 8, northbound
15-Oct-08
15-Oct-08
Hard shoulder closure from 0900 - 1600 hrs for communications works for Midlands TechMAC
Lane Closure
M5
Junction 1 northbound entry slip road
15-Oct-08
16-Oct-08
Lane 1 closure from 2100 - 0500 hrs for routine maintenance works
Lane Closure
M5
Junction 3 to junction 4, southbound
15-Oct-08
16-Oct-08
Lane 3 closure from 2100 - 0500 hrs for street lighting works
Lane Closure
M5
M6 junction 8 to M5 junction 1, southbound
15-Oct-08
16-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC
Lane Closure
M5
Junction 2 to junction 3, southbound
15-Oct-08
16-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC
Lane Closure
M5
Junction 3 to junction 4, southbound
16-Oct-08
17-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC (includes lane 2 on services slip road)
Lane Closure
M5
Junction 4 to junction 3, northbound
16-Oct-08
17-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC
Lane Closure
M5
Junction 4a, southbound
16-Oct-08
17-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC
Lane Closure
M5
Junction 7, southbound
17-Oct-08
18-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV Maintenance works for Midlands TechMAC
Lane Closure
M5
Junction 6, northbound
17-Oct-08
18-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV Maintenance works for Midlands TechMAC. To include lane closure on junction 6 island
Lane Closure
M5
Junction 5 to junction 4a, northbound
17-Oct-08
18-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC
Lane Closure
M5
Junction 5 to junction 6, southbound
17-Oct-08
18-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV maintenance works for Midlands TechMAC
Lane Closure
M50
Junction 1 and junction 2, eastbound
13-May-07
30-Jun-09
Hard shoulder closure 24 hours for safety due to embankment subsidence
Lane Closure
M50
Between junction 2 and 3
12-Nov-07
30-Jun-09
Hard shoulder closure in operation 2000 - 0630 hrs Changing to 24hr Closure from 04/12/2007 for upgrade to the VSF
Lane Closure
M50
Junction 1 to junction 2, both directions
31-Aug-08
17-Jan-09
24-hour lane 1 or 2 closures from 31/8/09 - 18/09/08 then contraflow from 19/9/08 for Queenhill Viaduct Major Maintenance Scheme. Works consist of barrier replacement, verge reconstruction, new kerbs, re-waterproofing and resurfacing (40mph speed limit)
Contraflow
M50
Various locations
6-Oct-08
16-Oct-08
Hard shoulder closure in operation 2000 - 0600 hrs for sweeping
Lane Closure
M54
M6 Junction 10a to M54 junction 2, both directions
13-Oct-08
31-Oct-08
Weekday hard shoulder closures from 0930 - 1530 hrs as part of the signal and Midas upgrade works (Pre-PHASE 1 works)
Lane Closure
M54
Junction 2 to junction 7, both directions
13-Oct-08
18-Oct-08
Nightly mobile lane 1 or 2 closures as required from 2100 - 0500 hrs for electrical repairs and sweeping at various locations
Mobile Lane Closure
M54
Junction 7, eastbound
14-Oct-08
15-Oct-08
Lane 1 closure followed by lane 2 closure as required from 2100 - 0600 hrs for CCTV Maintenance works for Midlands TechMAC. To include lane closure on J7 exit slip road
Lane Closure
M54
Junction 6 to junction 7, westbound
14-Oct-08
15-Oct-08
Lane 1 closure from 2100 - 0600 hrs for CCTV Maintenance works for Midlands TechMAC
Lane Closure
M54
Junction 2 to junction 3, both directions
14-Oct-08
15-Oct-08
Lane 1 closures from 2100 - 0500 hrs for carriageway inspections
Lane Closure
M54
Junction 3 to junction 5, both directions
15-Oct-08
16-Oct-08
Lane 2 closures from 2100 - 0500 hrs for centre signal maintenance works for Midlands TechMAC
Lane Closure
M6
Junction 4 to junction 5, both directions
27-Aug-08
31-Oct-09
Various daily & nightly 24 hour closures for ATM works to include narrow lanes, hard shoulder running and 50mph speed limit
Lane Closure
M6
Junction 6 to junction 7, northbound
7-Oct-08
20-Oct-08
Nightly lane 1 and 2 closures from 2100 - 0500 hrs for carriageway joint replacement works
Lane Closure
M6
Junction 10a to junction 11, both directions
13-Oct-08
31-Oct-08
Weekday hard shoulder closures from 0930 - 1530 hrs as part of the signal and Midas upgrade works (Pre-PHASE 1 works)
Lane Closure
M6
Junction 4 to junction 12, both directions
13-Oct-08
15-Oct-08
Daily mobile hard shoulder closures from 0930 - 1530 hrs for electrical works
Mobile Lane Closure
M6
Junction 10a to junction 10, southbound
13-Oct-08
17-Oct-08
Various nightly closures from 2100 - 0500 hrs for carriageway resurfacing
Lane Closure
M6
Junction 8 to junction 9, northbound
13-Oct-08
15-Oct-08
Nightly hard shoulder or lane 3 running as required from 2100 - 0500 hrs for carriageway resurfacing. To include FULL overnight closure of M5 north to M6 north link road at junction 8
Carriageway Closure
M6
Junction 10 to junction 12, northbound
13-Oct-08
18-Oct-08
Nightly lane 1 closures from 2100 - 0500 hrs for pre ATM Ground investigation works at various locations
Lane Closure
M6
Junction 5 to junction 4a, southbound
13-Oct-08
18-Oct-08
Nightly lane 1 closures from 2100 - 0500 hrs for pre ATM Ground investigation works at various locations
Lane Closure
M6
Junction 10 to junction 9, southbound
14-Oct-08
15-Oct-08
Daily hard shoulder closures from 0830 - 1700 hrs for cable replacement
Lane Closure
M6
Junction 9 northbound entry slip road
14-Oct-08
15-Oct-08
Lane 1 closure from 2100 - 0600 hrs for communications works for Midlands TechMAC
Lane Closure
M6
Junction 10 to junction 9, southbound
15-Oct-08
18-Oct-08
Nightly hard shoulder closures from 0830 - 1700 hrs for cable replacement
Lane Closure
M6
Junction 10 Island, north side of bridge
16-Oct-08
17-Oct-08
Daily lane 1 closure from 0930 - 1530 hrs for removal of pedestrian barrier and safety fence repairs
Lane Closure
M6
Junction 10 northbound exit slip road
16-Oct-08
17-Oct-08
Lane 1 closure from 2100 - 0500 hrs for electrical works
Lane Closure
M6
Junction 8 to junction 9, northbound
17-Oct-08
18-Oct-08
Hard shoulder or lane 3 running as required from 2100 - 0500 hrs for carriageway resurfacing. To include FULL overnight closure of M5 north to M6 north link road at junction 8
Carriageway Closure