East Midlands motorway and trunk road works programme – Monday 8 to Sunday 14 February 2010

M1 JUNCTION 25 TO JUNCTION 28 WIDENING

ONGOING – JUNCTION 25 TO JUNCTION 26

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit from Junction 25 to 26.

Monday 8 Night/Tuesday 9 Morning

No further restrictions except in emergencies

Tuesday 9 Night/Wednesday 10 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 9/10 February, for communications work.

Wednesday 10 Night/Thursday 11 Morning

Northbound junction 26 exit slip road closed overnight 9pm to 5am 10/11February, for surfacing and communications work.
Northbound reduced to a single lane in some places overnight 10pm to 5am 10/11 February, for communications work.

Thursday 11 Night/Friday 12 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 11/12 February, for gantry work and sign erection.
Northbound junction 26 exit slip road closed overnight 9pm to 5am 11/12 February, for surfacing work.
Southbound junction 26 entry slip road closed overnight 9pm to 5am 11/12 February, for surfacing work.

Friday 12 Night/Saturday 13 Morning

Northbound junction 26 exit slip road closed overnight 9pm to 5am 12/13 February, for surfacing work.
Southbound junction 26 entry slip road closed overnight 9pm to 5am 12/13 February, for surfacing work

Saturday 13 Night/Sunday 14 Morning

No further restrictions except in emergencies

Sunday 14 Night/Monday 15 Morning

No further restrictions except in emergencies

ONGOING – JUNCTION 26 TO JUNCTION 27

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit. Traffic will be running on the hard shoulder, lanes 1 and 2 both northbound and southbound.

Monday 8 Night/Tuesday 9 Morning

Northbound reduced to a single lane in some places overnight 10pm to 5am 8/9 February, for communications work.
Southbound reduced to a single lane in some places overnight 10pm to 5am 8/9 February, for surfacing work.

Tuesday 9 Night/Wednesday 10 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 9/10 February, for surfacing work.

Wednesday 10 Night/Thursday 11 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 10/11 February, for gantry work.

Thursday 11 Night/Friday 12 Morning

Northbound reduced to a single lane in some places overnight 10pm to 5am 11/12 February, for communications work.

Friday 12 Night/Saturday 13 Morning

No further restrictions except in emergencies

Saturday 13 Night/Sunday 14 Morning

No further restrictions except in emergencies

Sunday 14 Night/Monday 15 Morning

No further restrictions except in emergencies

ONGOING – JUNCTION 27 TO JUNCTION 28

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit.

Monday 8 Night/Tuesday 9 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 8/9 February, for communications work.
Northbound reduced to a single lane in some places overnight 10pm to 5am 8/9 February, for surfacing work and movement of temporary barrier.

Tuesday 9 Night/Wednesday 10 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 9/10 February, for gantry and communications work.
Northbound reduced to a single lane in some places overnight 10pm to 5am 9/10 February, for surfacing work and movement of temporary barrier.

Wednesday 10 Night/Thursday 11 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 10/11 February, for gantry and communications work.
Northbound reduced to a single lane in some places overnight 10pm to 5am 10/11 February, for surfacing work and movement of temporary barrier.

Thursday 11 Night/Friday 12 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 11/12 February, for gantry and communications work.
Northbound reduced to a single lane in some places overnight 10pm to 5am 11/12 February, for surfacing work and movement of temporary barrier.

Friday 12 Night/Saturday 13 Morning

Northbound reduced to a single lane in some places overnight 11pm to 5am 12/13 February, for gantry and communications work.
Southbound reduced to a single lane in some places overnight 11pm to 5am 12/13 February, for surfacing work and movement of temporary barrier.

Saturday 13 Night/Sunday 14 Morning

No further restrictions except in emergencies

Sunday 14 Night/Monday 15 Morning

No further restrictions except in emergencies

A1 PETERBOROUGH TO BLYTH JUNCTION IMPROVEMENTS

ONGOING – REPAIR WORKS TO BE CARRIED OUT AT A1/A614 BLYTH

The Highways Agency is carrying out repair work to the A1 at Blyth Junction (A1/A614) as a consequence of a major lorry fire incident that occurred at the junction.

Works will be required in early 2010 to repair concrete pipes affected by the fire and to clean up any contamination that is found. Further details will be confirmed when the programme and scope of repairs is fully determined.

For more information about the A1 Peterborough to Blyth Junction Improvements and to sign up for regular updates please visit:

http://www.highways.gov.uk/roads/projects/4455.aspx

NEW, AMENDED AND ONGOING WORKS

DERBYSHIRE

NEW – A38 SLIP ROAD – B600 SOMERCOTES

Overnight slip road safety improvement works which will include traffic signing, road markings, high friction surfacing and cutting back of vegetation.

Works will begin 15 February to 3 March, from 8pm to 6am; noisy works will be restricted to 8pm to 11pm to avoid nuisance to residents.

Start point for roadworks, west of A38 / A61 Derby Road Watchorn junction northbound off-slip, and end point for roadworks A38 / M1 Junction 28 junction.

Closure of northbound on/off slip road from A38 to B600 Nottingham Road – A38(T) north and southbound lane 1 closure.

Traffic Management:

A38 mainline lane 1 closure and speed 50mph restriction only required to undertake part of the construction work. Mainline restrictions will be lifted once this is complete. Slip closure will be required throughout the works period.

Closures to be phased as follows: Northbound off and southbound on to be closed at same time. Northbound on and southbound off to be closed at same time.

NEW – A38 SOMERCOTES

Temporary speed restriction, convoy working and lane closures north and southbound for signing and lining works. Overnight works will take place from Monday 15 February to Wednesday 3 March, 8pm to 6am.

NEW – A38 SLIPROAD CLOSURE AT HARTSHAY NEAR RIPLEY

Work will start on Monday 1 February evening to renew a high friction road surface and install yellow bar markings across the slip roads from the A38 to the A610 at Hartshay near Ripley in Derbyshire.

The road works will be in place from 8pm on Monday 1 February to 6am on Tuesday 12 February. There will also be 50mph, 30mph and 10mph speed restrictions in places with convoy working while traffic management is on the carriageway.

While the slip roads are closed the following diversions will be in place:

A38 Southbound slip road to the A610:

Traffic travelling southbound on the A38 wishing to exit for the A610 at Hartshay should continue southbound to the Coxbench junction. Road users should then turn right and continue along the B6179 for approximately 300m and turn right to rejoin the A38 northbound and continue towards the junction with the A610 where the diversion ends.

A38 Northbound slip road to the A610:

Traffic travelling northbound along the A38 and wishing to exit for the A610 should continue for the junction with the A61 towards Alfreton. At the roundabout join the A38 southbound carriageway and continue to the exit with the A610 where the diversion ends.

ONGOING – A5111 RAYNESWAY RIVER BRIDGE

Contraflow or lane closures to be in place from Wednesday 13 January for both north and south directions, along with a 30 mph speed restriction for bridge maintenance. 24/7 traffic management will be in place, however removed for bank holidays. Works are scheduled to run until Monday 19 April.

ONGOING – A38 TOYOTA TO A516 SAFETY FENCE

A scheme to replace central reserve safety fencing and two small sections of nearside safety fencing was due to be completed on Saturday 30 January 2010.  The works are over running due to time lost to weather in early January and also other unforeseen reasons. The works are now anticipated to be completed by Monday 1 March.

In order to minimise disruption to road users, all work will be done between 8pm and 6am when the traffic flow is at the lightest.

To allow for the works to take place safely and to ensure safety of the travelling vehicles, a 40mph speed restriction is in place 24 hours a day.

There will be overnight lane 1 or lane 2 closures as required.

ONGOING – COXBENCH ILLUMINATED SPEED SIGNS

The proposed works consist of illuminating the regulatory speed signs on all four slip roads at A38 / B6179 slip Roads at Coxbench.

The work will take place from Sunday 28 February 2010 to Friday 19 March 2010, from 8pm to 6am.

There will be southbound entry slip and northbound entry slip road closures and the other slip roads will have lane one and lane two closures as required.

Diversion route:

Traffic from the B6179 northbound onto the A38 will be diverted onto the A38 southbound and round Little Eaton Roundabout.

Traffic from the B6179 South bound onto the A38 will be kept on the B6179, sent through Little Eaton then onto the A38 at Little Eaton Roundabout.

ONGOING – A50 JUNCTION 4 (TOYOTA)

Slip road closure eastbound and westbound from Monday 4 January until Friday 30 April 2010 between 9pm to 5am, for junction modifications.

ONGOING – A50 JUNCTION 3 CHELLASTON

Slip road closure to Eastbound from Monday 4 January until Friday 30 April 2010 between 9pm to 5am, for junction modifications.

ONGOING – A5111 RAYNESWAY

New dual carriageway link and major Junction improvements at Raynesway Park began in August 2009 and will continue until autumn 2010.

The work will provide access to the new Derby Commercial Park which is being built alongside Raynesway and the A6 Alvaston Bypass, and reduce congestion on this route at peak times.

Traffic management will be installed at different locations and different times while the scheme progresses.

Raynesway River Bridge

Contraflow or lane closures in place both north and southbound, along with a 30mph speed restriction for bridge maintenance, 24/7 traffic management will be in place (removed for bank holidays). Works are scheduled to run until Monday 17 May.

LEICESTERSHIRE

NEW – A1 BLOODY OAKS TO STRETTON

Carriageway closure northbound for resurfacing works. Overnight works from Monday 1 February to Saturday 20 February, 8pm to 6am. There is a diversion route in place with temporary signs erected on the nights.

ONGOING – A46 AT GROBY

A scheme to resurface a section of the A46 will take place between Friday 22 January and Thursday 4 February from 8pm to 6am.

There will also be a 50mph speed limit in place 24hours a day.

The A46 Groby resurfacing scheme is located on the southbound carriageway between the end of the A46/A563 entry slip road and will continue to the start of the exit slip for the M1 Junction 21a.

ONGOING – M1 JUNCTION 22 EXIT SLIP ROADS

Lane 2 or hard shoulder closure for traffic signs and road marking works, Friday 22 January to Saturday 13 February, 9.30am to 3.30pm.

ONGOING – M1 JUNCTION 19 TO JUNCTION 15

Various lane closures with hard shoulder running and slip road closures. The work began in November 2009 and will run until Friday 2 April 2010 between 8pm and 6am.

ONGOING – M1 JUNCTION 19 TO JUNCTION 18

Various lane closures with hard shoulder running, slip road closures at Junction 19 and Junction 18 and 50mph speed restrictions. Work began in November 2009 and will run until Friday 2 April 2010 between 8pm and 6am.

ONGOING – A50 JUNCTION 1 SAWLEY

Slip road closure Westbound Monday 16 November to Wednesday 31 March 2010 between 9pm to 5am, for junction modifications.

LINCOLNSHIRE

NEW – A1 LONG BENNINGTON

The scheme is located on the lay-bys on the A1 Southbound at Long Bennington.

It is proposed to resurface the footpaths adjacent to the lay-bys and resurface one of the lay-bys just south of the entry slip at Long Bennington.

Overnight works will begin Thursday 18 to Sunday 28 February from 8pm to 6am.

The works will be done under Lane 1 closures and lay-by closures with in the scheme extents.

NOTTINGHAMSHIRE

NEW – A52 GAMSTON TO SAXONDALE

Main carriageway improvement works – erection of 2 new illuminated traffic signs with associated cabling and ducting works, between Gamston and Saxondale Roundabouts near Ratcliffe on Trent.

Overnight works will take from Sunday 7 to Friday 19 February between 8pm to 6am.

Traffic management will be in place:

Eastbound – Lane 1 closure on Dual Carriageway Section of the A52

Westbound –  four-way temporary traffic lights at the junction of Cropwell Road and the A52.

ONGOING – A46 CROPWELL BUTLER TO SCREVETON

Major works for the widening of the carriageway until Monday 30 April 2012 between 4.30pm to 6am. This will include carriageway closures, temporary traffic lights, speed restrictions, verge working and works off the carriageway.

ONGOING – A46 WIDMERPOOL TO CROPWELL BUTLER

Major works for the widening of the carriageway, this will include carriageway closure, temporary traffic lights, speed restrictions, verge workings and works off the carriageway. The work is due to take place until Thursday 30 April 2012.

ONGOING – A46 SCREVETON (LODGE LANE) TO FARNDON

Major works for the widening of the carriageway, this will include carriageway closure, temporary traffic lights, speed restrictions, verge workings and works off the carriageway. The work is due to take place until Thursday 30 April 2012.

NORTHAMPTONSHIRE

NEW – M1 JUNCTION 15 TO 19, WATFORD GAP SERVICE

Overnight closures to the north and southbound carriageway of the M1 Motorway near Watford Gap services. The southbound entry and exit slip roads and the northbound entry slip road of Watford Gap services will be closed to enable essential maintenance to be carried out to.

These closures are required to ensure the safety of the travelling public and also our workforce.

Southbound:

Planned works will be in place on the evenings of Wednesday 17 and Thursday 18 February, Saturday 20 and Saturday 27 March.

Access to the Southbound Service Area via the M1 southbound carriageway will not be possible between the hours of Wednesday 17 & Thursday 18 February between 10pm and 5am, and Saturday 20 and 27 March – 8pm and 9am.

Northbound:

Planned works will be carried out on the evening of Friday 12 February.

Access to the Northbound Service Area via the M1 norththbound carriageway will not be possible between the hours of 11pm and 7am.

NEW – A45 WILBY WAY SEGREGATED LEFT TURN

Removal of existing countdown markers in the central reservation, and the installation of new countdown markers at revised locations within the central reservation.

Off side lane of the A45 to be affected due to single lane closure by traffic management. Works will begin Monday 15 to Tuesday 23 February from 9pm to 6am.

Traffic Management:

Lane 2 closure, dual carriageway with or without a hard shoulder – relaxed offside lane closure.

NEW – M1 JUNCTION 16 TO 15

Various lane closures with hard shoulder running due to slip road closures at Junction 15a and 15, 50mph speed restriction is in place. Overnight works from Monday 1 February to Friday 2 April, 9pm to 6am.

ONGOING – A14 CORRIDOR TRAFFIC MANAGEMENT SCHEME

A14 nightly closures Monday 1 to Friday 5 February from 8pm to 6am.

A14 eastbound lane 1 closure between the M1 Junction 19 Catthorpe Interchange and Junction 1, Monday, Tuesday, and Wednesday nights.

A14 eastbound lane 1 closure between Junctions 11 and 13, Monday to Thursday nights.

A14 eastbound lane 1 closure between Junctions 11 and 12, Friday night.

A14 westbound lane 1 closure between Junctions 13 and 12.

A14 westbound lane 1 closure between Junctions 9 and 7.

A14 westbound lane 1 closure between Junction 1 and the M1 Junction 19 Cathorpe Interchange, Thursday and Friday nights.

A45 northbound two-way temporary traffic light closure between the Raunds roundabout and the A45/A14 interchange.

ONGOING – M1 JUNCTION 18 TO JUNCTION 17

Various lane closures with hard shoulder running, slip road closures at Junction 17 and 50 mph speed restrictions. The work is due to take until Thursday 1 April from 8pm to 6am.

ONGOING – A5 TOWCESTER

Temporary lights for water works 24/7. Work will take place from Monday 18 January to Thursday 11 February from 9.30am to 3.30pm.

ONGOING – M1 JUNCTION 17 TO JUNCTION 16

Various lane closures with hard shoulder running, slip road closures at Junction 16 and 50 mph speed restrictions. The work is due to take place until Thursday 1 April 2010 with closures between 8pm and 6am.

GENERAL

Between now and the end of March there will be a significant increase in roadworks in the East Midlands, as we continue to invest in maintaining and improving the region’s motorways and major A roads. We will do as much work as we can overnight (generally between 8pm and 6am) when traffic flows are at a minimum, but some work has to take place during the day for safety reasons. We will minimise delays by keeping as many lanes open as possible while the work takes place. For up to date information about roadworks which may affect your journey visit www.highways.gov.uk/area7bbf