East Midlands motorway and trunk road works programme – Monday 15 to Sunday 21 February 2010

M1 JUNCTION 25 TO JUNCTION 28 WIDENING

ONGOING – JUNCTION 25 TO JUNCTION 26

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit from Junction 25 to 26.

Monday 15 Night/Tuesday 16 Morning

Northbound junction 26 exit slip road closed overnight 9pm to 5am 15/16 February, for surfacing work Southbound junction 26 entry slip road closed overnight 9pm to 5am  15/16 February, for surfacing work

Tuesday 16 Night/Wednesday 17 Morning

No further restrictions except in emergencies

Wednesday 17 Night/Thursday 18 Morning

Southbound junction 25 exit slip road reduced to one lane 9.30am to 3pm 17/18 February, for sign erection Southbound reduced to a single lane in some places overnight 10pm to 5am 17/18 February, for surfacing and movement of temporary barrier

Thursday 18 Night/Friday 19 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 18/19 February, for surfacing and movement of temporary barrier

Friday 19 Night/Saturday 20 Morning

Southbound reduced to a single lane in some places overnight 11pm to 5am 19/20 February, for surfacing and movement of temporary barrier

Saturday 20 Night/Sunday 21 Morning

No further restrictions except in emergencies

Sunday 21 Night/Monday 22 Morning

No further restrictions except in emergencies

ONGOING – JUNCTION 26 TO JUNCTION 27

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit. Traffic will be running on the hard shoulder, lanes one and two both northbound and southbound.

Monday 15 Night/Tuesday 16 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 15/16 February, for communications work Northbound junction 27 exit slip road reduced to a single lane 9.30am to 4pm 15/16 February, for communications and sign work Northbound reduced to a single lane in some places overnight 10pm to 5am 15/16 February, for traffic management changes

Tuesday 16 Night/Wednesday 17 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 16/17 February, for communications work Northbound junction 27 exit slip road reduced to a single lane 9.30am to 4pm 16/17 February, for communications and sign work Northbound reduced to a single lane in some places overnight 10pm to 5am 16/17 February, for traffic management changes Southbound junction 26 exit slip road closed overnight 9pm to 5am  16/17 February, for surfacing work Northbound junction 26 entry slip road closed overnight 9pm to 5am  16/17 February, for surfacing work

Wednesday 17 Night/Thursday 18 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 17/18 February, for communications work Southbound junction 26 exit slip road closed overnight 9pm to 5am  17/18 February, for traffic management changes Northbound junction 26 entry slip road closed overnight 9pm to 5am  17/18 February, for traffic management changes

Thursday 18 Night/Friday 19 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 18/19 February, for communications work Southbound junction 26 exit slip road closed overnight 9pm to 5am  18/19 February, for traffic management changes Northbound junction 26 entry slip road closed overnight 9pm to 5am  18/19 February, for traffic management changes

Friday 19 Night/Saturday 20 Morning

Southbound reduced to a single lane in some places overnight 11pm to 5am 19/20 February, for communications work

Saturday 20 Night/Sunday 21 Morning

No further restrictions except in emergencies

Sunday 21 Night/Monday 22 Morning

No further restrictions except in emergencies

ONGOING – JUNCTION 27 TO JUNCTION 28

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit.

Monday 15 Night/Tuesday 16 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 15/16 February, for surfacing work and movement of temporary barrier

Tuesday 16 Night/Wednesday 17 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 16/17 February, for surfacing work and movement of temporary barrier

Wednesday 17 Night/Thursday 18 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 17/18 February, for surfacing work and movement of temporary barrier

Thursday 18 Night/Friday 19 Morning

Northbound reduced to a single lane in some places overnight 10pm to 5am 18/19 February, for surfacing work and movement of temporary barrier

Friday 19 Night/Saturday 20 Morning

Northbound reduced to a single lane in some places overnight 11pm to 5am 19/20 February, for gantry and communications work

Saturday 20 Night/Sunday 21 Morning

No further restrictions except in emergencies

Sunday 21 Night/Monday 22 Morning

No further restrictions except in emergencies

A1 PETERBOROUGH TO BLYTH JUNCTION IMPROVEMENTS

ONGOING – REPAIR WORKS TO BE CARRIED OUT AT A1/A614 BLYTH

The Highways Agency is carrying out repair work to the A1 at Blyth Junction (A1/A614) as a consequence of a major lorry fire incident that occurred at the junction.

The final stage of repair works will involve a 38 hour full closure of the A1 southbound carriageway at Blyth Junction. During the closure southbound A1 traffic will be diverted onto the southbound exit and entry slip roads to maintain traffic flows. All other traffic movements at the junction will be maintained. These works are scheduled to be completed between either the Friday 19 and Sunday 21 February, or Friday 26 and Sunday 28 February. Works should commence at 10pm on Fridays and be completed by 12pm on the Sunday. Further details will be confirmed when the programme for the works is finalised.

For more information about the A1 Peterborough to Blyth Junction Improvements and to sign up for regular updates please visit:

http://www.highways.gov.uk/roads/projects/4455.aspx

NEW, AMENDED AND ONGOING WORKS

DERBYSHIRE

NEW – A38 SOMERCOTES

Temporary speed restriction, convoy working and lane closures north and southbound for signing and lining works. Overnight works will take place from Monday 15 February to Wednesday 3 March, 8pm to 6am.

ONGOING – A38 HARTSHAY

Slip road closures and lane closures, also speed restrictions and convoy working north and southbound. Overnight works will begin Monday 1 February to Saturday 20 February between 8pm to 6am.

ONGOING – A38 SLIP ROAD – B600 SOMERCOTES

Overnight slip road safety improvement works which will include traffic signing, road markings, high friction surfacing and cutting back of vegetation.

Works will begin 15 February to 3 March, from 8pm to 6am; noisy works will be restricted to 8pm to 11pm to avoid nuisance to residents.

Start point for , west of A38 / A61 Derby Road Watchorn junction northbound exit slip, and end point for A38 / M1 Junction 28 junction.

Closure of northbound entry/exit slip road from A38 to B600 Nottingham Road – A38(T) north and southbound lane one closure.

Traffic Management:

A38 mainline lane one closure and 50mph speed restriction required to undertake part of the construction work. Restrictions will be lifted once this is complete. Slip closure will be required throughout the works period.

Closures to be phased as follows: Northbound exit and southbound entry to be closed at same time. Northbound entry and southbound exit to be closed at same time.

ONGOING – A5111 RAYNESWAY RIVER BRIDGE

Contraflow or lane closures to be in place from Wednesday 13 January for both north and south directions, along with a 30 mph speed restriction for bridge maintenance. 24/7 traffic management will be in place, however removed for bank holidays. Works are scheduled to run until Monday 19 April.

ONGOING – COXBENCH ILLUMINATED SPEED SIGNS

The proposed works consist of illuminating the regulatory speed signs on all four slip roads at A38 / B6179 slip Roads at Coxbench.

The work will take place from Sunday 28 February to Friday 19 March, from 8pm to 6am.

There will be southbound entry slip and northbound entry slip road closures and the other slip roads will have lane one and lane two closures as required.

Diversion route:

Traffic from the B6179 northbound onto the A38 will be diverted onto the A38 southbound and round Little Eaton Roundabout.

Traffic from the B6179 South bound onto the A38 will be kept on the B6179, sent through Little Eaton then onto the A38 at Little Eaton Roundabout.

ONGOING – A50 JUNCTION 4 (TOYOTA)

Slip road closure eastbound and westbound from Monday 4 January until Friday 30 April 2010 between 9pm to 5am, for junction modifications.

ONGOING – A50 JUNCTION 3 CHELLASTON

Slip road closure to Eastbound from Monday 4 January until Friday 30 April 2010 between 9pm to 5am, for junction modifications.

ONGOING – A5111 RAYNESWAY

New dual carriageway link and major junction improvements at Raynesway Park began in August 2009 and will continue until autumn 2010.

The work will provide access to the new Derby Commercial Park which is being built alongside Raynesway and the A6 Alvaston Bypass, and reduce congestion on this route at peak times.

Traffic management will be installed at different locations and different times while the scheme progresses.

Raynesway River Bridge

Contraflow or lane closures in place both north and southbound, along with a 30mph speed restriction for bridge maintenance, 24/7 traffic management will be in place (removed for bank holidays). Works are scheduled to run until Monday 17 May.

LEICESTERSHIRE

NEW – A1 SOUTHBOUND EXIT SLIP TO A6060 STAMFORD

This essential carriageway work involves resurfacing the A1 southbound exit/entry slip to the A606 along with renewing the lines and road studs. The work starts at the exit taper on the A1 and finishes at the exit slips junction with the A606 Stamford.

Overnight closures will be in place from Saturday 20 to Wednesday 24 February from 8pm to 6am.

Traffic management will be in place:

Closure of southbound exit/entry slip road to A606 50mph speed limit on A1 southbound carriageway on approach to exit slip Closure of lane 1 on the A1 southbound in the location of the exit/entry slip closures Sydney Farm Lane/A606 entry/exit slip junction closure

ONGOING – A1 BLOODY OAKS TO STRETTON

Carriageway closure northbound for resurfacing works. Overnight works from Monday 1 February to Saturday 20 February, 8pm to 6am. There is a diversion route in place with temporary signs erected on the nights.

ONGOING – M1 JUNCTION 19 TO JUNCTION 15

Various lane closures with hard shoulder running and slip road closures. The work began in November 2009 and will run until Friday 2 April 2010 between 8pm and 6am.

ONGOING – M1 JUNCTION 19 TO JUNCTION 18

Various lane closures with hard shoulder running, slip road closures at Junction 19 and Junction 18 and 50mph speed restrictions. Work began in November 2009 and will run until Friday 2 April 2010 between 8pm and 6am.

ONGOING – A50 JUNCTION 1 SAWLEY

Slip road closure Westbound Monday 16 November to Wednesday 31 March 2010 between 9pm to 5am, for junction modifications.

LINCOLNSHIRE

ONGOING – A1 LONG BENNINGTON

The scheme is located on the lay-bys on the A1 Southbound at Long Bennington.

It is proposed to resurface the footpaths adjacent to the lay-bys and resurface one of the lay-bys just south of the entry slip at Long Bennington.

Overnight works will begin Thursday 18 to Sunday 28 February from 8pm to 6am.

The works will be done under lane one closures and lay-by closures with in the scheme extents.

NOTTINGHAMSHIRE

ONGOING – A52 GAMSTON TO SAXONDALE

Main carriageway improvement works – erection of two new illuminated traffic signs with associated cabling and ducting works, between Gamston and Saxondale roundabouts near Ratcliffe on Trent.

Overnight works will take from Sunday 7 to Friday 19 February between 8pm to 6am.

Traffic management will be in place:

Eastbound – Lane one closure on Dual Carriageway Section of the A52

Westbound – four-way temporary traffic lights at the junction of Cropwell Road and the A52.

ONGOING – A46 CROPWELL BUTLER TO SCREVETON

Major works for the widening of the carriageway until Monday 30 April 2012 between 4.30pm to 6am. This will include carriageway closures, temporary traffic lights, speed restrictions, verge working and works off the carriageway.

ONGOING – A46 WIDMERPOOL TO CROPWELL BUTLER

Major works for the widening of the carriageway, this will include carriageway closure, temporary traffic lights, speed restrictions, verge workings and works off the carriageway. The work is due to take place until Thursday 30 April 2012.

ONGOING – A46 SCREVETON (LODGE LANE) TO FARNDON

Major works for the widening of the carriageway, this will include carriageway closure, temporary traffic lights, speed restrictions, verge workings and works off the carriageway. The work is due to take place until Thursday 30 April 2012.

NORTHAMPTONSHIRE

ONGOING – M1 JUNCTION 15 TO 19, WATFORD GAP SERVICE

Overnight closures to the north and southbound carriageway of the M1 Motorway near Watford Gap services. The southbound entry and exit slip roads and the northbound entry slip road of Watford Gap services will be closed to enable essential maintenance to be carried out to.

These closures are required to ensure the safety of the travelling public and also our workforce.

Southbound:

Planned works will be in place on the evenings of Wednesday 17 and Thursday 18 February, Saturday 20 and Saturday 27 March.

Access to the Southbound Service Area via the M1 southbound carriageway will not be possible between the hours of Wednesday 17 & Thursday 18 February between 10pm and 5am, and Saturday 20 and 27 March – 8pm and 9am.

Northbound:

Planned works will be carried out on the evening of Friday 12 February.

Access to the Northbound Service Area via the M1 norththbound carriageway will not be possible between the hours of 11pm and 7am.

ONGOING – A45 WILBY WAY SEGREGATED LEFT TURN

Removal of existing countdown markers in the central reservation, and the installation of new countdown markers at revised locations within the central reservation.

Off side lane of the A45 to be affected due to single lane closure by traffic management. Works will begin Monday 15 to Tuesday 23 February from 9pm to 6am.

Traffic Management:

Lane two closure, dual carriageway with or without a hard shoulder – relaxed offside lane closure.

ONGOING – M1 JUNCTION 16 TO 15

Various lane closures with hard shoulder running due to slip road closures at Junction 15a and 15, 50mph speed restriction is in place. Overnight works from Monday 1 February to Friday 2 April, 9pm to 6am.

ONGOING – M1 JUNCTION 18 TO JUNCTION 17

Various lane closures with hard shoulder running, slip road closures at Junction 17 and 50 mph speed restrictions. The work is due to take until Thursday 1 April from 8pm to 6am.

ONGOING – M1 JUNCTION 17 TO JUNCTION 16

Various lane closures with hard shoulder running, slip road closures at Junction 16 and 50 mph speed restrictions. The work is due to take place until Thursday 1 April 2010 with closures between 8pm and 6am.

GENERAL

Between now and the end of March there will be a significant increase in roadworks in the , as we continue to invest in maintaining and improving the region’s motorways and major A roads. We will do as much work as we can overnight (generally between 8pm and 6am) when traffic flows are at a minimum, but some work has to take place during the day for safety reasons. We will minimise delays by keeping as many lanes open as possible while the work takes place. For up to date information about roadworks which may affect your journey visit www.highways.gov.uk/area7bbf