East Midlands motorway and trunk road works programme – Monday 22 to Sunday 28 march 2010

EASIER WHEELCHAIR ACCESS FOR LAY-BYS

The Highways Agency is to construct new drop kerbs at lay-bys across the East Midlands to allow easier access for wheelchair users.

The scheme will continue on the A14 from the M1 to the A6116 from Monday, 15 March. All work will be completed by Wednesday, 31 March.

Work will take place in lay-bys between 8am and 5pm or 8pm and 6am, depending on their location. The speed limit in the main carriageway will be reduced to 50mph for the safety of roadworkers and road users during the night time work. The lay-bys will also be closed during the work.

M1 JUNCTION 25 TO JUNCTION 28 WIDENING

M1 Junction 24A – Junction 25

Monday 22 Night/Tuesday 23 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 22/23 March, for surfacing work Northbound reduced to a single lane in some places overnight 10pm to 5am 22/23 March, for surfacing work Northbound junction 25 exit slip road closed overnight 9pm to 5am 22/23 March, for surfacing work

Tuesday 23 Night/Wednesday 24 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 23/24 March, for surfacing work Northbound reduced to a single lane in some places overnight 10pm to 5am 23/24 March, for surfacing work Northbound junction 25 exit slip road closed overnight 9pm to 5am 23/24 March, for surfacing work

Wednesday 24 Night/Thursday 25 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 24/25 March, for surfacing work Northbound reduced to a single lane in some places overnight 10pm to 5am 24/25 March, for surfacing work Northbound junction 25 exit slip road closed overnight 9pm to 5am 24/25 March, for surfacing work

Thursday 25 Night/Friday 26 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 25/26 March, for surfacing work Northbound reduced to a single lane in some places overnight 10pm to 5am 25/26 March, for surfacing work Northbound junction 25 exit slip road closed overnight 9pm to 5am 25/26 March, for surfacing work

Friday 26 Night/Saturday 27 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 26/27 March, for surfacing work Northbound reduced to a single lane in some places overnight 10pm to 5am 26/27 March, for surfacing work Northbound junction 25 exit slip road closed overnight 9pm to 5am 26/27 March, for surfacing work

Saturday 27 Night/Sunday 28 Morning

No further restrictions except in emergencies

Sunday 28 Night/Monday 29 Morning

No further restrictions except in emergencies

ONGOING – JUNCTION 25 TO JUNCTION 26

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit from Junction 25 to 26.

Monday 22 Night/Tuesday 23 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 22/23 March, for bridge work, barrier work and movement of temporary barrier Northbound lane three closed in some places overnight 9pm to 5am 22/23  March, for barrier work

Tuesday 23 Night/Wednesday 24 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 23/24  March, for bridge work, barrier work and movement of temporary barrier Northbound lane three closed in some places overnight 9pm to 5am 23/24  March, for barrier work

Wednesday 24 Night/Thursday 25 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 24/25  March, for bridge work, barrier work and movement of temporary barrier Northbound lane three closed in some places overnight 9pm to 5am 24/25  March, for barrier work

Thursday 25 Night/Friday 26 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 25/26 March, for bridge work, barrier work and movement of temporary barrier Northbound lane three closed in some places overnight 9pm to 5am 25/26  March, for barrier work

Friday 26 Night/Saturday 27 Morning

Southbound reduced to a single lane in some places overnight 11pm to 5am 26/27 March, for bridge work, barrier work and movement of temporary barrier Northbound lane three closed in some places overnight 10pm to 5am 26/27 March, for barrier work

Saturday 27 Night/Sunday 28 Morning

No further restrictions except in emergencies

Sunday 28 Night/Monday 29 Morning

No further restrictions except in emergencies

ONGOING – JUNCTION 26 TO JUNCTION 27

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit. Traffic will be running on the hard shoulder, lanes one and two both northbound and southbound.

Monday 22 Night/Tuesday 23 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 22/23 March, for communications and gantry work

Tuesday 23 Night/Wednesday 24 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 23/24 March, for communications and gantry work

Wednesday 24 Night/Thursday 25 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 24/25 March, for communications and gantry work

Thursday 25 Night/Friday 26 Morning

Southbound reduced to a single lane in some places overnight 10pm to 5am 25/26 March, for communications and gantry work

Friday 26 Night/Saturday 27 Morning

Southbound reduced to a single lane in some places overnight 11pm to 5am 26/27 March, for communications and gantry work Northbound reduced to a single lane in some places overnight 11pm to 5am 26/27 March, for communications and gantry work

Saturday 27 Night/Sunday 28 Morning

No further restrictions except in emergencies

Sunday 28 Night/Monday 29 Morning

No further restrictions except in emergencies

ONGOING – JUNCTION 27 TO JUNCTION 28

The north and southbound carriageways continue to be reduced to three narrow lanes with no hard shoulder and a 50mph speed limit.

Monday 22 Night/Tuesday 23 Morning

Northbound reduced to a single lane in some places overnight 11pm to 5am 22/23 March, for communications and gantry work

Tuesday 23 Night/Wednesday 24 Morning

Northbound reduced to a single lane in some places overnight 11pm to 5am 23/24 March, for communications and gantry work

Wednesday 24 Night/Thursday 25 Morning

Northbound reduced to a single lane in some places overnight 11pm to 5am 24/25 March, for communications and gantry work Northbound junction 28 exit slip road closed overnight 9pm to 5am 24/25 March, for surfacing and communications work

Thursday 25 Night/Friday 26 Morning

Northbound reduced to a single lane in some places overnight 11pm to 5am 25/26 March, for communications and gantry work

Friday 26 Night/Saturday 27 Morning

Northbound junction 27 exit slip road closed overnight 9pm to 5am 26/27 March, for surfacing and communications work

Saturday 27 Night/Sunday 28 Morning

No further restrictions except in emergencies

Sunday 28 Night/Monday 29 Morning

No further restrictions except in emergencies

NEW, AMENDED AND ONGOING WORKS

DERBYSHIRE

ONGOING – A5111/A6 OFF NETWORK DIVERSION ROUTE

At various locations on the A5111, A52 and A6, installation of various new off network diversion route signs, and diversion symbols using existing traffic signs.

Overnight works began Monday 15 March to Monday 1 April from 9am to 3.30pm (day time working) on A6, 8pm to 6am (night time working) on A5111, and 8pm to 6am (night time working) on A52.

Maximum of two miles at each location will be affected:

A5111 Raynesway – A6 London Road

A52 eastbound & westbound in the vicinity of Spondon Interchange

In addition to temporary lane closures, pedestrians will require escorting through the traffic management in residential areas.

ONGOING – A38 MARKEATON ROUNDABOUT

A scheme to resurface just over 2 miles of the A38 between Markeaton Roundabout and the junction with the A6 in Derby begin on Thursday 11 March.

The overnight works between 8pm and 6am will replace the road surface on the northbound carriageway, and also renew the road markings and road studs.

A full carriageway closure is required on the northbound A38 between the Markeaton Roundabout and the A38 northbound entry slip road from the A6. The northbound exit slip roads to Kedleston Road and Palm Court Roundabout will also be closed. The work is due to be complete on Thursday 25 March.

ONGOING – A50 JUNCTION 4 (TOYOTA)

Slip road closure eastbound and westbound from Monday 4 January until Friday 30 April 2010 between 9pm to 5am, for junction modifications.

ONGOING – A50 JUNCTION 3 CHELLASTON

Slip road closure to eastbound from Monday 4 January until Friday 30 April 2010 between 9pm to 5am, for junction modifications.

ONGOING – A5111 RAYNESWAY

New dual carriageway link and major junction improvements at Raynesway Park began in August 2009 and will continue until autumn 2010.

The work will provide access to the new Derby Commercial Park which is being built alongside Raynesway and the A6 Alvaston Bypass, and reduce congestion on this route at peak times.

Traffic management will be installed at different locations and different times while the scheme progresses.

Raynesway River Bridge

Contraflow or lane closures in place both north and southbound, along with a 30mph speed restriction for bridge maintenance, 24/7 traffic management will be in place (removed for bank holidays). Works are scheduled to run until Monday 19 April.

LEICESTERSHIRE

ONGOING – M1 JUNCTION 21A AND 21

Lane and slip road closures southbound for communications work. Early morning closures from Monday 22 to Wednesday 24 March 2am to 5.30am.

ONGOING – M1 JUNCTION 22 AND 21A

Lane closures with hard shoulder running, slip road closure and 50mph speed restrictions. The overnight works start Thursday 18 March, to Thursday 1 April from 10pm to 6am.

ONGOING – M1 NETWORK DIVERSION ROUTE SIGNS, STAGE THREE WORKS

Installations of new network diversion route signs and diversion symbols at various locations, on the exit slip roads of Junction 24 of the M1 near Kegworth and at two other locations in the vicinity of A50/B6540 junction near Hemington in Leicestershire.

Daytime works will run 9am to 3.30pm and night works will run 8pm 6am.

Lanes affected:

Hard shoulder and lane one of the M1 junction 24 northbound exit slip Hard shoulder and lane one of the M1 junction 24 southbound exit Slip Lane one of the A453 south east approach to junction 24 of the M1 Lane one of A453 eastbound exit at junction 24 of the M1 Lane one of the A50 westbound entry slip Lane one of the A50 eastbound exit slip

ONGOING – A46 CARRIAGEWAY IMPROVEMENTS BETWEEN RATCLIFFE AND SIX HILLS

Construction work to rebuild and resurface a 2.8-mile section of the northbound A46 in Leicestershire started on Monday 22 February.

The work takes place 24 hours a day, seven days a week until Friday 30 April on the northbound carriageway followed by some daytime lane closures for another two weeks. The works will be completed in two sections.

For the first section, traffic management will start just north of the Six Hills café and petrol station and continue to the north of the A46/B676 Six Hills junction. The traffic management involves a contraflow system with northbound traffic running on the southbound carriageway for the duration of the works in this section. The work and all traffic management will be lifted for the Easter holidays.

The second section of traffic management will be installed after the Easter break on 12 April. This will cover the stretch of carriageway from south of Seagrave crossroads to north of Six Hills junction. The contraflow system with northbound traffic running on the southbound carriageway will be in place for approximately three weeks, followed by lane closures.

During the four overnight closures of the southbound carriageway traffic will be diverted along the A606 and A607.  The diversion route will be clearly signed.

ONGOING – M1 JUNCTION 19 TO JUNCTION 15

Various lane closures with hard shoulder running and slip road closures. The work began in November 2009 and will run until Friday 2 April 2010 between 8pm and 6am.

ONGOING – M1 JUNCTION 19 TO JUNCTION 18

Various lane closures with hard shoulder running, slip road closures at junction 19 and junction 18 and 50mph speed restrictions. Work began in November 2009 and will run until Friday 2 April 2010 between 8pm and 6am.

ONGOING – A50 JUNCTION 1 SAWLEY

Slip road closure Westbound Monday 16 November to Wednesday 31 March 2010 between 9pm to 5am, for junction modifications.

LINCOLNSHIRE

ONGOING – A1 COLSTERWORTH TO STOKE ROCHFORD

Overnight carriageway closure on the northbound carriageway for resurfacing, works are due to start Saturday 20 March to Wednesday 31 March, from 10pm to 6am.

NOTTINGHAMSHIRE

ONGOING – A453 OFF NETWORK DIVERSION ROUTE

At various locations on the M1, A453, A52 and A6, installations of various new off network diversion route signs, and diversion symbols using existing traffic signs.

Overnight works began Thursday 18 March to Thursday 1 April, from 8pm to 6am.

Maximum of 2 miles at each location will be affected:

M1 northbound – junction 24 – 25

A52 east and westbound in the vicinity of Clifton Bridge

A453 in the vicinity of Crusader Roundabout

A6 northbound prior to M1 junction 24

ONGOING – A46 WINTHORPE RESURFACING

A scheme to resurface Winthorpe roundabout and repair sections of the A46 carriageway near Winthorpe will start on Monday 22 March.

The work will take place overnight between 8pm to 6am for four nights, but while the resurfacing and carriageway patching takes place there will be lane and carriageway closures.

From Monday 22 to Friday 26 March the A46 dedicated northbound lane between the A1/A46 roundabout and the A17/A46/A1 roundabout will be closed. The north and southbound A46 carriageways from the A46/A17/A1 roundabout to the Winthorpe roundabout will also be closed.

One half of the Winthorpe roundabout will remain open as required for traffic to be controlled using temporary traffic lights and a 30mph speed restriction through the roundabout.

In addition, the A46 northbound and southbound will be closed at the roundabout. The A46 southbound carriageway will be closed from the A46/Middle Lane/A1434 Roundabout to the Winthorpe roundabout, and the southbound entry slip from Brough Lane will also be closed.

ONGOING – A52 BARDILL’S TO JUNCTION 25

Various slip road, roundabout and lane closures in both directions for electrical works east and westbound from Monday 8 March to Tuesday 20 April, 8pm to 6am.

ONGOING – A52 RADCLIFFE ON TRENT LANE CLOSURES

Work to replace the electricity supply to safety bollards at the Harlequin Junction on the A52 at Radcliffe on Trent started on Saturday 6 March.

The work involves replacing the existing electrical cable which is underneath the road surface, so the westbound carriageway will be closed and all traffic will use the eastbound carriageway controlled using temporary traffic lights.

The traffic lights at the junction will also be replaced by the temporary traffic lights, but while work is not taking place, the junction will return to normal operation.

The scheme is expected to be completed by Tuesday 30 March with work taking place during the weekend between 7am and 7pm and overnight on week days between 8pm and 6am.

ONGOING – A46 CROPWELL BUTLER TO SCREVETON

Major works for the widening of the carriageway until Monday 30 April 2012 between 4.30pm to 6am. This will include carriageway closures, temporary traffic lights, speed restrictions, verge working and works off the carriageway.

ONGOING – A46 WIDMERPOOL TO CROPWELL BUTLER

Major works for the widening of the carriageway, this will include carriageway closure, temporary traffic lights, speed restrictions, verge workings and works off the carriageway. The work is due to take place until Monday 30 April 2012.

ONGOING – A46 SCREVETON (LODGE LANE) TO FARNDON

Major works for the widening of the carriageway, this will include carriageway closure, temporary traffic lights, speed restrictions, verge workings and works off the carriageway. The work is due to take place until Monday 30 April 2012.

ONGOING – A1/A614 BLYTH JUNCTION

Repair works to fire damaged drainage, single lane closures of the A1 southbound carriageway for 1km to the north of the junction between 8pm and 6am on Thursday 25, Friday 26 and Saturday 27 March.

NORTHAMPTONSHIRE

NEW – A14 CORRIDOR TRAFFIC MANAGEMENT SCHEME

Traffic management for the week commencing Monday 22 to Friday 28 March.

Section 1 – 8pm to 6am nightly

Scheme 2

A14 eastbound lane one closure between junctions two and four

Scheme 3

A14 westbound lane one closure between junctions 10 and eight

Scheme 4

A14 eastbound lane one closure between junctions 12 and 14, Junction 13 eastbound exit slip will be fully closed, diversion via a14 eastbound to junction 16 then return on A14 westbound to junction 13

Section 2 – 8pm to 6am nightly

Scheme 9

A14 eastbound lane one closure between junctions 35 and 37; from Monday 22 and Tuesday 23 March (please note that a lane one closure is required on the A11 northbound between six mile bottom and the A11/A14 eastbound interchange)

A14 eastbound lane one closure between junctions 36 and 37; from Wednesday 24 night

A14 eastbound lane one and two closure between junctions 37 and 39, from Monday 22 and Tuesday 23 March

A11 northbound lane one closure from Six Mile bottom to the A11/A14 interchange at junction 36 of the A14; from Tuesday 23 night

A11 Northbound from the Waterhall interchange to Dane Hill Road interchange

A11 southbound from Dane Hill Road interchange to the Waterhall interchange

A14 westbound lane one closure between junctions 39 and 37

A14 westbound lane one and two closure junctions 37 and 35, (please note that a lane 1 closure is required on the A11 southbound from the A14/A11 interchange at junctions 36 westbound)

Scheme 10

A14 eastbound lane one closure between junctions 41 and 44

A14 westbound lane one closure between junctions 46 and 45

A14 westbound lane one closure between junctions 42 and 40

Section 3 – 8pm to 6am nightly

Scheme 13

A14 eastbound lane one closure between junctions 59 and 62

A14 westbound lane one closure between junctions 62 and 59

Scheme 12

A14 eastbound lane one closure between junctions 53 and 55

A14 eastbound lane one closure between junctions 56 and 58

A14 westbound lane one closure between junctions 58 and 56

A14 westbound lane one closure between junctions 54 and 51

Scheme Z

A14 westbound lane one closure between junctions 51 and 49

ONGOING – A45 STANWICK ROUNDABOUT RESURFACING

Overnight resurfacing to the Stanwick roundabout westbound approach; junction nearest village of Stanwick – near Wellingborough. Works will be carried out 24 to 25 March between 9pm to 6am.

The westbound carriageway (single carriageway road) will be closed between Raunds roundabout and Stanwick roundabout. Part of the circulatory carriageway at Stanwick roundabout will be closed thereby restricting movements to traffic using the eastbound carriageway and traffic exiting Stanwick.

Local traffic coming from the north into Raunds and Stanwick will have to use Raunds roundabout. Local traffic from the south will have to travel up to Raunds roundabout, there is no entrance from Stanwick roundabout.

Westbound traffic will be diverted westbound along the A14, then south on to the A510 to Finedon, then onto the A6 in a south easterly direction towards Higham Ferrers to join back on to the A45.

ONGOING – A43 GAYTON

Lane one closure southbound Tuesday 22 to Wednesday 23 March 10pm to 6am, for carriageway reconstruction works.

ONGOING – A14 JUNCTION 1 TO M1 JUNCTION 19 FILTER DRAIN RENEWALS

The existing filter drain stone within the eastbound and westbound verges and central reserve will be excavated, cleaned, and replaced in one operation, thereby improving the drainage conditions.

Overnight works began 15 March to 11 April, from 8pm to 6am Monday to Thursday, 9pm to 8am Friday, 7pm to 10am Saturday, 9pm to 6am Sunday.

50mph speed limit will be in effect for the duration of the works, also traffic management will be as follows:

Lane Closures

Lane one eastbound when works are within eastbound verge

Lane one westbound when works are within westbound verge

Lane two eastbound and westbound when works are within central reserve

Lay-by Closures

Lay-by closures when works are within the east and westbound verges

Slip Road Closures With Diversion

A14 junction one eastbound exit slip road closure for one night

A14 junction one westbound entry slip road closure for one night

ONGOING – M1 JUNCTION 15 TO 19, WATFORD GAP SERVICE

M1 JUNCTION 15 TO 19 SOUTHBOUND SLIP ROAD & CARRIAGEWAY CLOSURES

As part of a major scheme to resurface a section of the M1 in Northamptonshire, there will be various lane closures with hard shoulder running and slip road closures. The work began in November 2009 and will run until Friday 2 April between 8pm and 6am.

There will be the following closures on the dates listed below:

Junction 16 exit slip:

Monday 22 March, 9pm to 5am

Tuesday 23 March, 9pm to 5am

Wednesday 24 March, 9pm to 5am

Thursday 25 March, 9pm to 5am

Full Carriageway closures between junction 18 to 16:

Junction 18 entry slip, the M45 and Watford Gap Services

Saturday 27 March, 8pm to 9am

The start time of these closures are subject to change and depend on both the weather and volume of traffic using the M1.

The southbound entry and exit slip roads and the northbound entry slip road of Watford Gap services will be closed to enable essential maintenance to be carried out.

Access to the Southbound Service Area via the M1 southbound carriageway will not be possible between the hours of Saturday 20 and 27 March – 8pm and 9am.

These closures are required to ensure the safety of the travelling public and also our workforce.

ONGOING – M1 JUNCTION 16 TO 15

Various lane closures with hard shoulder running due to slip road closures at Junction 15a and 15, 50mph speed restriction is in place. Overnight works from Monday 1 February to Friday 2 April, 9pm to 6am.

ONGOING – M1 JUNCTION 17 TO JUNCTION 16

Various lane closures with hard shoulder running, slip road closures at Junction 16 and 50mph speed restrictions. The work is due to take place until Thursday 1 April 2010 with closures between 8pm and 6am.

ONGOING – M1 JUNCTION 18 TO JUNCTION 17

Various lane closures with hard shoulder running, slip road closures at Junction 17 and 50mph speed restrictions. The work is due to take until Thursday 1 April from 8pm to 6am.

ONGOING – M1 JUNCTION 19 TO JUNCTION 18

Various lane closures with hard shoulder running, slip road closures at junction 19 and 18 and 50mph speed restrictions. The work is due to take until Thursday 1 April from 8pm to 6am.

GENERAL

Between now and the end of March there will be a significant increase in in the East Midlands, as we continue to invest in maintaining and improving the region’s motorways and major A roads. We will do as much work as we can overnight (generally between 8pm and 6am) when traffic flows are at a minimum, but some work has to take place during the day for safety reasons. We will minimise delays by keeping as many lanes open as possible while the work takes place. For up to date information about which may affect your journey visit www.highways.gov.uk/area7bbf