NEW, AMENDED AND ONGOING WORKS

DERBYSHIRE

Ongoing – A5111 Raynesway, new dual carriageway and major junction improvements

Start Date: August 2009 End Date: December 2010

Times: N/A

Traffic Management:

A5111 southbound traffic diverted via new slip roads and roundabout (Alvaston road users via the newly constructed bridge).

· A5111 northbound traffic continues to the west of the original road to go to Alvaston or Derby but access to the commercial park, A6 south and the A50 is via the bridge.

LEICESTERSHIRE

Ongoing – A14/M1 Catthorpe Roundabout, resurfacing works

Start Date: Friday, 19 November End Date: Monday, 6 December

Times: Fridays from 10.00pm to Mondays at 5.00am

Traffic Management: M1 and M6 entry and exit slip roads and carriageway closure for roundabout resurfacing works.

Ongoing – M1/M6 Catthorpe Viaduct replacement, M1 Junction 19

Start Date: Monday, 12 July 2010 End Date: April 2012

Times: 24/7 with various other closures to be implemented.

Traffic Management:

· M1 northbound, traffic running on lanes two and three only with a 50mph speed limit between the M6 northbound exit slip road, up to junction 19 of the M1.

· Southbound, traffic running at two narrower lanes only (hard shoulder and lane one) with a 50mph speed limit between the A14 exit slip road and the M6 entry slip road.

· Lane closure and 50 mph speed limit on the M6 southbound from just after the A14 exit slip road until where the M6 joins the M1.

· Speed restrictions are in place on the M6 from west of the A14 exit slip road up to the A5 underpass which reduces the speed limit from 70, to 60 and then 50mph.

NORTHAMPTONSHIRE

New – A43 Brackley, resurfacing

Start Date: Tuesday, 23 November End Date: Tuesday, 30 November

Times: 10.00pm to 6.00am

Traffic Management: Overnight works to resurface roundabouts at Oxford Road, Buckingham Road and Northampton Road. A43 will be closed in both directions with diversion route following A5, A422, A413 and A421.

Ongoing – A14/M1 Catthorpe Roundabout, resurfacing works

Start Date: Friday, 19 November End Date: Monday, 6 December

Times: Fridays from 10.00pm to Mondays at 5.00am

Traffic Management: M1 and M6 entry and exit slip roads and carriageway closure for roundabout resurfacing works.

Ongoing – A43 Barley Mow Roundabout, resurfacing

Start Date: Weds, 17 November End Date: Thurs, 16 December

Times: 10.00pm to 6.00am

Traffic Management: Overnight carriageway closure both north and southbound.

Ongoing – A45, Barnes Meadow Interchange, Northampton, improvements to interchange and trunk road

Start Date: Monday, 18 October End Date: March 2011

Times: 8.00pm to 6.00am

Traffic Management: Traffic management to include overnight off-peak road and lane closures and temporary traffic lights.

Ongoing – M1/M6 Catthorpe Viaduct replacement, M1 Junction 19

Start Date: Monday, 12 July 2010 End Date: April 2012

Times: 24/7 with various other closures to be implemented.

Traffic Management:

· M1 northbound, traffic running on lanes two and three only with a 50mph speed limit between the M6 northbound exit slip road, up to junction 19 of the M1.

· Southbound, traffic running at two narrower lanes only (hard shoulder and lane one) with a 50mph speed limit between the A14 exit slip road and the M6 entry slip road.

· Lane closure and 50 mph speed limit on the M6 southbound from just after the A14 exit slip road until where the M6 joins the M1.

· Speed restrictions are in place on the M6 from west of the A14 exit slip road up to the A5 underpass which reduces the speed limit from 70, to 60 and then 50mph.

NOTTINGHAMSHIRE

Ongoing – A46 Newark to Widmerpool, Newton Lane near junction with A6097

Start Date: Monday, 25 October End Date: end November

Times: 24/7

Traffic Management: Newtown Lane near the Margidunum roundabout will be closed for this period as part of the widening works

Ongoing – A46 Newark to Widmerpool, widening the carriageway, Saxondale roundabout

Start Date: Friday, 8 October End Date: Winter 2011

Times: 24/7

Traffic Management: Traffic approaching the Saxondale roundabout from both the A46 and A52 is being diverted using both the new and existing roundabouts before heading back to continue the journey on the existing carriageways.

Ongoing – A46 Newark to Widmerpool, widening the carriageway

Cropwell Butler to Screveton
Widmerpool to Cropwell Butler
Screveton (Lodge Lane) to Farndon

Start Date: September 2009 End Date: April 2012

Times: 4.30pm to 6am

Traffic Management: Carriageway closures, temporary traffic lights, speed restrictions, verge working and works off the carriageway.

Ongoing – A46 Newark to Widmerpool, widening the carriageway, Stragglethorpe junction

Start Date: Friday, 25 June End Date: Summer 2011

Times: 24/7

Traffic Management: Traffic is diverted via the new northbound entry and exit slip roads, and via the new western roundabout as appropriate. All traffic management is signed for road users.